Oil Drillers Eye Mexico Expansion Despite Contract
Delays In October, Petroleos Mexicanos said it would rent five
large offshore rigs, grabbing the attention of local and foreign rig
suppliers.
A week later, Pemex withdrew the rate tenders to make
revisions, underscoring the rewards and difficulties of working for Mexico's
state-run oil monopoly. Pemex is spending more on oil equipment and services
to revive the struggling industry. This creates new opportunities for oil
services firms, but bureaucratic hurdles can also delay project startups for
months. "They're going to roll it out again, but we don't know
when," said a Mexico-based executive at a foreign firm that plans to compete
for the upcoming contracts. Rig suppliers such as Schlumberger Ltd., Noble Corp. and
Diamond Offshore Drilling expect to see the tenders reemerge before the end
of the year, and are generally upbeat on the outlook for Mexico. Mexican oil production is in steep decline as the
country's most accessible oil formations run dry. This means the country
must drill a larger number of wells at less-prolific oil fields just to
stabilize output. Pemex plans to double exploration spending over the next
three years, expanding the opportunities for oil service firms that have
worked in Mexico for decades. "As far as we can tell it is still full steam ahead, so
you've got to love Pemex," said Noble Corp. CEO David Williams in a recent
conference call. "They need the hydrocarbons, so you don't expect to see a
lot of pullback there." Noble plans to compete for the five rigs when Pemex
publishes the new terms. Pemex delayed a contract for 600 wells in the
Chicontepec basin by around five months until May 2008, when it was awarded
to Weatherford International Ltd. Pemex CEO Jesus Reyes Heroles recently
said the delay contributed to the company's failure to meet production
targets for this year. Output has fallen 10% to under 2.8 million barrels a
day. Bronco Drilling has described similar delays at a
smaller project where it has three rigs under an 18-month contract. "We have faced numerous delays in commencing operations,
but we do believe that all three rigs will begin work during the fourth
quarter," Bronco Drilling CEO Frank Harrison said in a recent conference
call. Pemex has already made some progress. During the first
nine months of this year it expanded its rig fleet 8.5% to 242, more than
half of which are owned by independent contractors. Pemex also increased the
number of offshore platforms 5.1% to 226, including those that house workers
and provide telecommunications services. This spending has helped service providers, but Pemex is
only just starting to make up for lost ground. For decades it relied on one
field, Cantarell, for the bulk of total output, and the company spent little
exploring for and developing new oil deposits. With the Cantarell pumping less than half of peak
production as it enters old age, Pemex is scrambling to make up for lost
time. Some officials expect it to take a decade to restore overall
production to 2007 levels of 3 million barrels a day. Energy Minister
Georgina Kessel said Monday that the government will be happy just to halt
the decline for now. An energy reform passed last month will help. It will
streamline contracting procedures on the hopes of preventing delays such as
the recent rig tender withdrawal. Pemex also hopes to draw new players into the oil
industry with performance-based service contracts allowed under the reform.
Pemex needs help from international oil firms with experience in the deep
waters of the Gulf of Mexico. Pemex says around half of Mexico's
undiscovered oil lies in its underexplored section of the Gulf. Despite the hassles, Bronco Drilling expects to expand
in Mexico. "We continue to believe that Mexico could provide
opportunities for additional rigs in the future," said CEO Harrison.